Concrete U-Drain

Local Project - Quarter April-June 2020

🛈 Data Last Updated: 11/09/2020

-

Total Bids Received

Vernon Farrell

Contractor Awarded

-

Project Start Date

-

Projected End Date

Budget
$ 1
Spend to Date
$ 1

Description of Project

Construction of Reinforced Concrete Access Road with Curb & Slipper in Cheap End.

Project Activity Stage Description

Concrete U-Drain 100% Complete with Variations